Project 21DF0145
DPWH infrastructure contract
Contract ID:
21DF0145
Fingerprint:
3a32b3ea4a53da…f4fff1b250 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 12, 2021 (5 yrs 7 mo ago) · Target/actual end Oct 8, 2021
Description:
LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE/FACILITIESREHABILITATION OF MULTI-PURPOSE BUILDING, BRGY.BAGONG SILANG HEALTH CENTER, IMUS CITY ANDREHABILITATION OF MULTI-PURPOSE BUILDING, BRGY.MAHARLIKA,
Category:
Buildings and Facilities
Implementing office:
DPWH Cavite 1st DEO · Region IV-A
Contractor:
T.E. TRINIDAD CONSTRUCTION · DPWH contractor code 43287
Contract amount:
₱7,920,000.00 (₱7.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3ccddf5552f7… | Mar 29, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE I DEO | ₱7,520,536.50 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DQ0110 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DQ0111 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DF0158 | Jul 1, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS, | On-Going | ₱4.8M |
| 25DQ0084 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITE | On-Going | ₱96.0M |
| 25DQ0085 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITE | On-Going | ₱98.0M |
| 25DQ0090 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1) | On-Going | ₱98.0M |
| 25DQ0099 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3) | On-Going | ₱98.0M |
| 25DQ0101 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2) | On-Going | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.