Project 21DI0058
DPWH infrastructure contract
Contract ID:
21DI0058
Fingerprint:
b0e9f21077a26b…34272c8c75 Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start Jul 15, 2021 (5 yrs 3 mo ago) · Target/actual end Aug 12, 2022
Description:
OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0061+593 - K0061+860
Category:
Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP
Implementing office:
DPWH Laguna 2nd DEO · Region IV-A
Contractor:
L.P.O. ENTERPRISES · DPWH contractor code 20730
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7907d1bf08a2… | Jul 8, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LAGUNA II DEO | ₱11,114,386.64 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DI0060 | May 16, 2025 | CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY BAYBAYIN, LOS BANOS, LAGUNA | On-Going | ₱5.8M |
| 25DI0099 | Apr 3, 2025 | CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0058 + 774 - K0059 +359 | On-Going | ₱29.1M |
| 25DI0029 | Mar 31, 2025 | OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - MT MAKILING ECO GARDEN RD - K0061 + (-800) - K0061 + (-220) | On-Going | ₱36.1M |
| 25DI0048 | Mar 31, 2025 | CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0060 + 520 - K0062 + 000, K0063 + 231 - K0063 + 281 | On-Going | ₱62.4M |
| 25DI0054 | Mar 19, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, LOS BANOS, LAGUNA | On-Going | ₱10.7M |
| 25DI0069 | Mar 19, 2025 | CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY BAYOG, LOS BANOS, LAGUNA | On-Going | ₱6.8M |
| 25DI0024 | Feb 14, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0060 + 000 - K0061 + 000, K0063 + 671 - K0064 + 292 | Completed | ₱112.7M |
| 25DI0044 | Feb 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, ACADEMIC BUILDING, LSPU-LOS BANOS CAMPUS, BARANGAY MALINTA, LOS BANOS, LAGUNA | Completed | ₱7.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.