Project 21DK0108
DPWH infrastructure contract
Contract ID:
21DK0108
Fingerprint:
11f737ff91a5d3…0878210e45 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Apr 22, 2022
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BRGY. HALL), BARANGAY BONIFACIO, BURDEOS, QUEZON
Category:
Buildings and Facilities
Implementing office:
DPWH Quezon 1st DEO · Region IV-A
Contractor:
N.T. SOTELO CONSTRUCTION AND SUPPLY CORPORATION · DPWH contractor code 47269
Contract amount:
₱495,000.19 (₱495.0K)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DK0089 | Jun 11, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BURDEOS CENTRAL ELEMENTARY SCHOOL, BURDEOS, QUEZON | Completed | ₱2.5M |
| 25CP0069 | Apr 14, 2025 | CONVERGE. AND SPECIAL SUPPORT PROG. -SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADDS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONST. OF ROAD, PAHSE II SITIO BALIKIRAN, BARANGAY C | On-Going | ₱142.6M |
| 25DK0018 | Mar 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CABUNGALUNAN, BURDEOS, QUEZON | Completed | ₱2.5M |
| 25DK0002 | Feb 10, 2025 | CSSP - SIPAG (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY ALUYON - BARANGAY MABINI, BURDEOS, QUEZON | Completed | ₱24.2M |
| 24DK0129 | Jul 24, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MPB) AT BRGY. CABUGAO, BURDEOS, QUEZON | Completed | ₱3.9M |
| 24DK0120 | Jul 4, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. PALASAN, BURDEOS, QUEZON | Completed | ₱9.9M |
| 24DK0122 | Jul 4, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MPB) AT BRGY.AMOT, BURDEOS, QUEZON | Completed | ₱2.5M |
| 24DK0114 | Jul 3, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MPB) AT BRGY. CABUNGALUNAN, BURDEOS, QUEZON | Completed | ₱3.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.