FY2026 GAA: ₱6.79T
PisoScan

Project 21DN0078

DPWH infrastructure contract
Contract ID:
21DN0078
Fingerprint:
ae58a952b2e2fa…c336889290 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 15, 2021 (5 yrs 2 mo ago) · Target/actual end Apr 24, 2023
Description:
OO1: NETWORK DEVELOPMENT - OFF CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - CAINTA - KAYTICKLING - ANTIPOLO - TERESA - MORONG RD - K0021+000 - K0021+023, K0019+630 - K0019+670, K0018+022 - K0018+062, K0018+238 - K0018+370, CAINTA, RIZAL & TAYTAY, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
A.C. RIVERO DEVELOPMENT CORPORATION · DPWH contractor code 5122
Contract amount:
₱15,287,721.37 (₱15.3M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f076c27142d1…Sep 1, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED₱15,287,721.37

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25O00107Jun 5, 2025REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITYOn-Going₱189.1M
25OB0268May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5)On-Going₱14.0M
25OB0269May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6)On-Going₱14.0M
25OB0270May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7)On-Going₱14.0M
25DN0069Apr 8, 2025CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱19.6M
25DN0063Mar 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱9.7M
25DN0080Mar 27, 2025CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱15.2M
25DN0048Mar 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱49.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.