Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21DN0109

DPWH infrastructure contract
Contract ID:
21DN0109
Fingerprint:
0daa54e3feed1a…bc6e339e88 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Nov 18, 2022
Description:
CONSTRUCTION OF CREEK WALL PROTECTION, MALALIM NA SARA GOING TO SAN JUAN CREEK AT BRGY. MACAMOT AND BRGY. BATINGAN BINANGONAN, RIZAL
Category:
Flood Control and Drainage
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
GLJ CONSTRUCTION · DPWH contractor code 48842
Contract amount:
₱15,679,904.51 (₱15.7M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
12ed2d98f48e…Mar 21, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED₱14,892,660.09

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0097Jun 26, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT)On-Going₱7.1M
25DN0098May 29, 2025CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱19.0M
25DN0101May 29, 2025CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱9.5M
25DN0106May 29, 2025CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱4.9M
25DN0112May 29, 2025FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱2.6M
25DN0067May 27, 2025CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱67.5M
25DN0044May 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT)Completed₱19.6M
25DN0056May 26, 2025CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT)On-Going₱9.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.