Project 21DN0137
DPWH infrastructure contract
Contract ID:
21DN0137
Fingerprint:
05587e9551b340…fce0558e0b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 15, 2022 (4 yrs 8 mo ago) · Target/actual end Jun 26, 2023
Description:
ROAD WIDENING INCLUDING DRAINAGE - BINANGONAN - ANGONO - TAYTAY DIVERSION ROAD (ANGONO SECTION) ANGONO, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱96,499,941.21 (₱96.5M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f3a493eb325b… | Jan 21, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱94,086,934.03 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25O00107 | Jun 5, 2025 | REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | On-Going | ₱189.1M |
| 25OB0268 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5) | On-Going | ₱14.0M |
| 25OB0269 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6) | On-Going | ₱14.0M |
| 25OB0270 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7) | On-Going | ₱14.0M |
| 25DN0069 | Apr 8, 2025 | CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱19.6M |
| 25DN0063 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱9.7M |
| 25DN0080 | Mar 27, 2025 | CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱15.2M |
| 25DN0048 | Mar 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱49.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.