Project 21DN0147
DPWH infrastructure contract
Contract ID:
21DN0147
Fingerprint:
d019f62e26acc7…fc4b0aa7df Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 23, 2021 (5 yrs 2 mo ago) · Target/actual end Nov 20, 2021
Description:
CONCRETING OF SITIO KAYHABAGAT TO SITIO ACETONAS, BRGY. TATALA FMR, BRGY. TATALA BINANGONAN, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
T.J. VELASCO CONSTRUCTION & SUPPLY · DPWH contractor code 10560
Contract amount:
₱12,062,509.39 (₱12.1M)
Funding source:
Outside Infra - GAA 2021 DA FMR
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| da1820c01b16… | Aug 10, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱12,062,509.39 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0097 | Jun 26, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT) | On-Going | ₱7.1M |
| 25DN0098 | May 29, 2025 | CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱19.0M |
| 25DN0101 | May 29, 2025 | CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱9.5M |
| 25DN0106 | May 29, 2025 | CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱4.9M |
| 25DN0112 | May 29, 2025 | FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱2.6M |
| 25DN0067 | May 27, 2025 | CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱67.5M |
| 25DN0044 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱19.6M |
| 25DN0056 | May 26, 2025 | CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.