Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21DO0055

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","21DO0055","LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM- FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITIES - CONSTRUCTION OF RIPRAP IN BAUSTISTA CREEK BANLIK SUB URBAN VILLAGE SAN JOSE RODRGUEZ  RIZAL (PACKAGED)","Flood Control and Drainage","Completed",35640000,0,100,"Rizal 2nd DEO","Region IV-A","DOUBLE 12 CONSTRUCTION & SUPPLY (13028)","2022-09-05","2022-12-15",2021,"Regular Infra - GAA 2021 LP",14.75459,121.14062,"405808000","405800000"]
SHA-256
cd768794c87f8925232736ccc81bcaf7348436208b373f5d20d9d71360d766d8

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.