FY2026 GAA: ₱6.79T
PisoScan

Project 21DQ0120

DPWH infrastructure contract
Contract ID:
21DQ0120
Fingerprint:
3cabba7849ec05…2698cebfd2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 16, 2021 (4 yrs 11 mo ago) · Target/actual end Jun 13, 2022
Description:
CONSTRUCTION/COMPLETION OF 4STY8CL, MOLINO ELEMENTARY SCHOOL, BACOOR CITY, CAVITE
Category:
Buildings and Facilities
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
OMNICON BUILDERS · DPWH contractor code 22816
Contract amount:
₱23,070,754.25 (₱23.1M)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7188a01a8a97…Oct 28, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE 3RD DISTRIC₱22,603,245.80

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DQ0110Jul 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITEOn-Going₱9.8M
25DQ0111Jul 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITEOn-Going₱9.8M
25DF0158Jul 1, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS,On-Going₱4.8M
25DQ0084Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITEOn-Going₱96.0M
25DQ0085Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITEOn-Going₱98.0M
25DQ0090Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1)On-Going₱98.0M
25DQ0099Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3)On-Going₱98.0M
25DQ0101Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2)On-Going₱98.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.