Project 21E00027
DPWH infrastructure contract
Contract ID:
21E00027
Fingerprint:
a245b60cd6b2dc…50c1bbfd2c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 1, 2021 (5 yrs 6 mo ago) · Target/actual end Apr 9, 2022
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD, KO032+752.50-KO033+193.00, TABLAS ISLAND, ROMBLON
Category:
GAA 2021 OO-1
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
Location:
Contract amount:
₱143,751,208.86 (₱143.8M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0100 | May 22, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN ROQUE, CALATRAVA, ROMBLON | Completed | ₱3.9M |
| 25EH0035 | Mar 28, 2025 | CONSTRUCTION OF ROAD, BARANGAY BALOGO, CALATRAVA, ROMBLON | Completed | ₱9.6M |
| 25EH0047 | Mar 27, 2025 | REHABILITATION OF ROAD, PANGULO TO LINAO ROAD, CALATRAVA, ROMBLON | On-Going | ₱33.3M |
| 25EH0131 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALATRAVA, ROMBLON | On-Going | ₱29.1M |
| 25EH0045 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PAGSANGAHAN, CALATRAVA, ROMBLON | Completed | ₱2.9M |
| 25EH0005 | Mar 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ROMBLON STATE UNIVERSITY CALATRAVA CAMPUS, BARANGAY SAN ROQUE, CALATRAVA, ROMBLON | Completed | ₱4.9M |
| 24EH0061 | Jul 9, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD, CHAINAGE 39348 - CHAINAGE 39390, CHAINAGE 39396.26 - CHAINAGE 39397.66, TABLAS ISLAND, ROMBLON | Completed | ₱35.9M |
| 24EH0043 | Jun 19, 2024 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL ROAD, K0035+937.42 - K0036+418.17 AS PER ACTUAL, K0035+937.42 - K0036+422.17 AS PER RBIA, TABLAS ISLAND, ROMBLON | Completed | ₱6.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.