Project 21E00060
DPWH infrastructure contract
Contract ID:
21E00060
Fingerprint:
3e320058cd933f…6b6a0fd302 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 22, 2021 (5 yrs 3 mo ago) · Target/actual end Jul 9, 2022
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, KO005+170-KO005+234.90, SIBUYAN ISLAND, ROMBLON
Category:
GAA 2021 OO-1
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱67,549,540.93 (₱67.5M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0031 | May 26, 2025 | CONSTRUCTION OF CAMBALO FLOOD CONTROL STRUCTURE, CAJIDIOCAN, ROMBLON | On-Going | ₱48.3M |
| 25EH0115 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY DANAO, CAJIDIOCAN, ROMBLON | On-Going | ₱4.9M |
| 25EH0135 | May 22, 2025 | CONCRETING OF SITIO ALAHAG, BRGY. DANAO, FMR, BRGY. DANAO, CAJIDIOCAN, ROMBLON | On-Going | ₱39.1M |
| 25EH0039 | Apr 11, 2025 | CONSTRUCTION OF TAGUILOS CIS, SLOPE PROTECTION WORKS (UPSTREAM AND DOWNSTREAM, LEFT AND RIGHT SIDE EMBANKMENT), CAJIDIOCAN, ROMBLON | Completed | ₱9.7M |
| 25E00263 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG-BRGY. POBLACION, STA. 000+748.60-STA. 001+020, CAJIDIOCAMN, ROMBLON | On-Going | ₱230.9M |
| 25E00264 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG, STA. 000+398.65-STA. 000+440; STA. 000+520-STA. 000+740, CAJIDIOCAN, SIBUYAN IS | On-Going | ₱230.9M |
| 25EH0028 | Mar 25, 2025 | ACCESS ROAD LEADING TO CAJIDIOCAN VIEWDECK, CAJIDIOCAN, ROMBLON | Completed | ₱9.6M |
| 24EH0179 | Mar 24, 2025 | CONSTRUCTION OF LUMBANG WESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON | On-Going | ₱130.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.