Project 21EH0003
DPWH infrastructure contract
Contract ID:
21EH0003
Fingerprint:
9a6e3a8f5a19dc…631628d4fc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2021 (5 yrs 8 mo ago) · Target/actual end Oct 19, 2021
Description:
CONSTRUCTION OF MABULO FLOOD CONTROL STRUCTURE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, STA. 00 + 500 - 00 + 523.66 (R/S)/ STA. 00 + 523.66 - 00 + 576.13 (B/S) (SECTION 2)/ STA. 00 + 576.13 - 00 + 600 (B/S)/ STA. 00 + 600 - 00 + 663.50 (R/S) SECTION 1), S
Category:
GAA 2021 OO-2
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱19,095,540.92 (₱19.1M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0024 | Jul 28, 2025 | PAVING OF UNPAVED ROADS ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0031+421 - K0031+461, K0031+592 - K0031+632, K0039+013 - K0039+033.40 (AS PER ACTUAL & RBIA), SIBUYAN ISLAND, ROMBLON | Completed | ₱4.1M |
| 25EH0050 | May 23, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CABITANGAHAN BARANGAY TACLOBO, SAN FERNANDO, ROMBLON | On-Going | ₱145.5M |
| 25EH0080 | May 23, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CANTINGAS, SAN FERNANDO, ROMBLON | On-Going | ₱145.5M |
| 25EH0107 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT CAMPALINGO ELEMENTARY SCHOOL, SAN FERNANDO, ROMBLON | Completed | ₱2.0M |
| 25EH0126 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY TACLOBO, SAN FERNANDO, ROMBLON | On-Going | ₱4.9M |
| 25EH0040 | Apr 11, 2025 | CONSTRUCTION OF CAMPALINGO FLOOD CONTROL STRUCTURE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, PHASE 2, BRGY. CAMPALINGO, SAN FERNANDO, ROMBLON | On-Going | ₱27.1M |
| 25EH0009 | Mar 27, 2025 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUYAN CIRCUMFERENTIAL RD, K0010+829 - K0011+083 AS PER RBIA, K0010+829 - K0011+090 AS PER ACTUAL, SIBUYAN ISLAND, ROMBLON | Completed | ₱5.2M |
| 25EH0034 | Mar 24, 2025 | CONSTRUCTION OF PILI FLOOD CONTROL STRUCTURE PHASE 2, BARANGAY PILI, SAN FERNANDO, ROMBLON | On-Going | ₱141.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.