Project 21FH0051
DPWH infrastructure contract
Contract ID:
21FH0051
Fingerprint:
3a49a6082909a2…2cf246bcf0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 10, 2021 (5 yrs 8 mo ago) · Target/actual end Jun 5, 2021
Description:
ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS-PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING-CCR K0026+000-K0027+000
Category:
Roads
Implementing office:
DPWH Catanduanes DEO · Region V
Contractor:
AFC BUILDERS · DPWH contractor code 46843
Contract amount:
₱8,346,400.00 (₱8.3M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2ce93fce8434… | Feb 19, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CATANDUANES ED | ₱8,094,000.88 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FH0059 | Sep 4, 2025 | CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-I-A: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0028+000-K0028+647, K0028+788-K0029+000, K | On-Going | ₱218.7M |
| 25FH0041 | May 29, 2025 | BASIC INFRASTRUCTURE PROGRAMS (BIP) - PUBLIC WATER SUPPLY SYSTEM REHABILITATION OF WATER SUPPLY SYSTEM,BARANGAY BEGONIA AND BARANGAY BURGOS, VIGA, CATANDUANES | On-Going | ₱4.7M |
| 24F00011 | Nov 11, 2024 | CLUSTER XI-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-XI-I: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0003+060-K0003+648, K0003+658-K0 | On-Going | ₱262.5M |
| 24FH0041 | May 13, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, MUNICIPALITY OF PANGANIBAN, CATANDUANES | Completed | ₱5.8M |
| 24FH0033 | Apr 23, 2024 | BRIDGE-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, BANQUEROHAN BRIDGE (B00020CN) ALONG CATANDUANES CIRCUMFERENTIAL ROAD | Completed | ₱19.6M |
| 24FH0037 | Apr 23, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CATAGBACAN, SAN ANDRES, CATANDUANES | Completed | ₱4.6M |
| 24FH0021 | Apr 1, 2024 | BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, TOKIO BRIDGE ALONG CATANDUANES CIRCUMFRENTIAL ROAD | On-Going | ₱14.5M |
| 24FH0023 | Apr 1, 2024 | BRIDGE-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, QUIMBAG BRIDGE ALONG CATANDUANES CIRCUMFERENTIAL ROAD | On-Going | ₱17.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.