FY2026 GAA: ₱6.79T
PisoScan

Project 21GA0119

DPWH infrastructure contract
Contract ID:
21GA0119
Fingerprint:
e4efd830d19901…412cb44190 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 18, 2021 (5 yrs 5 mo ago) · Target/actual end Mar 9, 2022
Description:
CONSTRUCTION OF MPB BRGY. BANAYBANAY, MALINAO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
DAVE B. RELOJERO ARCHITECTS & ASSOCIATES · DPWH contractor code 34527
Contract amount:
₱1,481,593.69 (₱1.5M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
24b00caedb2d…May 7, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱1,481,593.09

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24GA0255Aug 7, 2025CONSTRUCTION OF SUGNOD-SIPAC FMR, BRGY. SUGNOD, MALINAO, AKLANOn-Going₱9.9M
25GA0147Aug 7, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PROVINCE OF AKLANOn-Going₱2.6M
25GA0120Jun 30, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BIGA-A, MALINAO, AKLANOn-Going₱1.3M
25GA0087Jun 19, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY NAVITAS, MALINAO, AKLANOn-Going₱3.0M
25GA0086Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BULABUD, MALINAO, AKLANOn-Going₱4.9M
25GA0088May 23, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY KINALANGAY VIEJO, MALINAO, AKLANOn-Going₱3.0M
25GA0129May 23, 2025CONSTRUCTION OF ROAD, BRGY. SUGNOD, MALINAO, AKLANOn-Going₱4.9M
24GA0247Mar 19, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MALINAO RIVER, BARANGAY BANAYBANAY, MALINAO, AKLANOn-Going₱86.0M