Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21GA0205

DPWH infrastructure contract
Contract ID:
21GA0205
Fingerprint:
c8c1adf8241d00…3e47ae058d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 15, 2021 (5 yrs 1 mo ago) · Target/actual end Jul 27, 2022
Description:
CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER BRGY. RIVERA, LIBACAO, AKLAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
PATRILA BUILDERS, INC. · DPWH contractor code 26628
Contract amount:
₱59,402,499.64 (₱59.4M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
81e163e7156f…Oct 6, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱59,302,058.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0135Aug 20, 2025CONCRETING OF BRGY. AGMAILIG FMR, BRGY. AGMAILIG, LIBACAO, AKLANOn-Going₱14.9M
25GA0053Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY CALAMCAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0060Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT/ EVACUATION CENTER), BARANGAY CALACABIAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0063Mar 19, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SIBALEW, LIBACAO, AKLANOn-Going₱4.9M
25GA0055Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY OGSIP, LIBACAO, AKLANOn-Going₱2.0M
25GA0058Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO AGBATUAN, BARANGAY OYANG, LIBACAO, AKLANOn-Going₱3.0M
25GA0062Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CASIT-AN, LIBACAO, AKLANOn-Going₱2.5M
25G00008Feb 14, 2025CONSTRUCTION OF MAGUGBA BRIDGE, BARANGAY POBLACION, LIBACAO, AKLANOn-Going₱192.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.