FY2026 GAA: ₱6.79T
PisoScan

Project 21GA0258

DPWH infrastructure contract
Contract ID:
21GA0258
Fingerprint:
2e44a800766bda…f3436eb79d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 15, 2021 (5 yrs 1 mo ago) · Target/actual end Mar 21, 2022
Description:
CONSTRUCTION (COMPLETION) OF 2STY4CL ALFONSO XII NHS BRGY. ALFONSO XII, LIBACAO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
BENZEN CONSTRUCTION · DPWH contractor code 41121
Contract amount:
₱525,827.20 (₱525.8K)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
be5b1fc7121f…Oct 7, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱525,827.20

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0135Aug 20, 2025CONCRETING OF BRGY. AGMAILIG FMR, BRGY. AGMAILIG, LIBACAO, AKLANOn-Going₱14.9M
25GA0053Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY CALAMCAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0060Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT/ EVACUATION CENTER), BARANGAY CALACABIAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0063Mar 19, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SIBALEW, LIBACAO, AKLANOn-Going₱4.9M
25GA0055Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY OGSIP, LIBACAO, AKLANOn-Going₱2.0M
25GA0058Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO AGBATUAN, BARANGAY OYANG, LIBACAO, AKLANOn-Going₱3.0M
25GA0062Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CASIT-AN, LIBACAO, AKLANOn-Going₱2.5M
25G00008Feb 14, 2025CONSTRUCTION OF MAGUGBA BRIDGE, BARANGAY POBLACION, LIBACAO, AKLANOn-Going₱192.6M