Project 21GD0044
DPWH infrastructure contract
Contract ID:
21GD0044
Fingerprint:
66a9440660950f…39515a315b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 25, 2021 (5 yrs 8 mo ago) · Target/actual end Aug 23, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY BINUNTUCAN, PONTEVEDRA, CAPIZ
Category:
Buildings and Facilities
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
STEP N STONE CONSTRUCTION · DPWH contractor code 35389
Contract amount:
₱4,943,629.26 (₱4.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f2f81f1feef2… | Feb 8, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO | ₱4,820,882.30 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0062 | Jul 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACAS, PONTEVEDRA, CAPIZ | On-Going | ₱6.9M |
| 25GD0050 | Jul 8, 2025 | PONTEVEDRA BY-PASS ROAD, CAPIZ | On-Going | ₱8.2M |
| 25GD0052 | Jul 8, 2025 | ROAD WIDENING - ILOILO EAST COAST-CAPIZ ROAD - KO146+781 - KO147+001 | Completed | ₱8.3M |
| 25G00071 | May 20, 2025 | CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY RIZAL, PONTEVEDRA, CAPIZ | On-Going | ₱48.2M |
| 25GD0028 | Mar 31, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION ILAWOD, PONTEVEDRA, CAPIZ | On-Going | ₱4.9M |
| 25GD0006 | Mar 24, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO EAST COAST - CAPIZ RD - KO135+778 - KO136+302 | On-Going | ₱8.5M |
| 25GD0014 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JOLONGAJOG, PONTEVEDRA, CAPIZ | On-Going | ₱4.9M |
| 24GD0067 | Nov 14, 2024 | CONCRETING OF SITIO CARINGALA, BRGY. JOLONGAJOG FMR, BRGY. JOLONGAJOG, PONTEVEDRA, CAPIZ | On-Going | ₱11.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.