Project 21GD0050
DPWH infrastructure contract
Contract ID:
21GD0050
Fingerprint:
9008edddb1fbbc…c68f3266cc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 3, 2021 (5 yrs 8 mo ago) · Target/actual end Jun 23, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DAYHAGAN, PILAR, CAPIZ
Category:
Buildings and Facilities
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
Contract amount:
₱2,940,007.61 (₱2.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| be398426e459… | Feb 17, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO | ₱2,940,007.61 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GH0153 | May 26, 2025 | CONSTRUCTION OF ABC BUILDING AT BARANGAY POBLACION, CARLES, ILOILO | Completed | ₱4.9M |
| 25GH0016 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY CABILAO GRANDE, CARLES, ILOILO | Completed | ₱2.0M |
| 25GH0042 | Mar 26, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY NALUMSAN, CARLES, ILOILO | Completed | ₱4.9M |
| 25GH0104 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY GUINTICGAN, CARLES, ILOILO | On-Going | ₱9.7M |
| 25GH0111 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD- CONSTRUCTION OF ROAD, BARANGAY BAROSBOS, CARLES, ILOILO | Completed | ₱9.8M |
| 25GH0093 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY GUINTICGAN, CARLES, ILOILO | Completed | ₱3.9M |
| 25GH0013 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY POBLACION, CARLES, ILOILO | Completed | ₱3.0M |
| 25GH0015 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY TUPAZ, CARLES, ILOILO | Completed | ₱3.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.