Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21GP0077

DPWH infrastructure contract
Contract ID:
21GP0077
Fingerprint:
a0ddb3b6f0b331…ed1e89fab0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 28, 2021 (4 yrs 10 mo ago) · Target/actual end Dec 12, 2022
Description:
CONSTRUCTION/COMPLETION OF 1STY5CL, DAPDAPAN ES, SAPI-AN, CAPIZ
Category:
Buildings and Facilities
Implementing office:
DPWH Capiz 2nd DEO · Region VI
Contractor:
7 JL HARDWARE & CONSTRUCTION SUPPLIES · DPWH contractor code 48378
Contract amount:
₱9,768,859.92 (₱9.8M)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1262b0f85ec4…Dec 15, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 2ND ED₱9,695,131.24

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GP0040Jun 5, 2025CONSTRUCTION OF CONCRETE ROAD, SITIO PASTUHAN BARANGAY AGSILAB, SAPIAN, CAPIZOn-Going₱9.7M
25GP0006Apr 5, 2025PREVENTIVE MAINTENANCE - SECONDARY ROADS ALONG CAPIZ AKLAN RD - K0333+270 - K0334+600On-Going₱36.4M
25GP0027Apr 5, 2025ROAD WIDENING- CAPIZ - AKLAN RD- K033+020- K0333+270On-Going₱19.0M
25GP0045Apr 5, 2025IMPROVEMENT OF INTERSECTION AT CAPIZ-AKLAN RD K0330 + 887On-Going₱14.4M
24GP0051Apr 8, 2024ROAD WIDENING CAPIZ-AKLAN ROAD - K0333+600 - K0333+860On-Going₱14.7M
24GP0019Feb 26, 2024ROAD WIDENING - CAPIZ-AKLAN RD - K0331+003 - K0331+038, K0331+085 - K0333+020Completed₱111.0M
24GP0023Feb 19, 2024ROAD WIDENING- CAPIZ- AKLAN ROAD- K0325+781- K0326+100, K0327+380- K0327+594, K0329+648- K0329+746, K0329+798- K0329+889, K0330+375- K0330+475, K0330+722- K0330+887, K0330+894- K0331+003On-Going₱57.9M
23GP0004May 25, 2023RECONSTRUCTION TO CONCRETE PAVEMENT ALONG CAPIZ-AKLAN RD (S00298PN) K0326+522 - K0327+402Completed₱55.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.