Project 21HA0041
DPWH infrastructure contract
Contract ID:
21HA0041
Fingerprint:
ae5b569695d978…b37dd9d699 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 12, 2021 (5 yrs 8 mo ago) · Target/actual end Jul 9, 2021
Description:
REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. WEST POBLACION, ALBURQUERQUE, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
RONNYL CONSTRUCTION · DPWH contractor code 38487
Contract amount:
₱2,789,783.09 (₱2.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24HA0141 | Aug 15, 2024 | RAINWATER COLLECTORS IN PUBLIC FACILITIES | Completed | ₱2.8M |
| 23HA0170 | May 15, 2024 | CONSTRUCTION OF STA. FELOMINA BEACH ROAD | Completed | ₱48.0M |
| 24HA0101 | May 15, 2024 | CONCRETING OF BRGY. BAHI TO BRGY. TORIL FMR, BRGY. BAHI AND BRGY. TORIL, ALBURQUERQUE, BOHOL | Completed | ₱24.9M |
| 23HA0106 | Aug 14, 2023 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) JCT. (TER) ALBURQUERQUE-SIKATUNA ROAD IN SUPPORT OF THE AGRIBUSINESS INDUSTRY, S | Completed | ₱120.5M |
| 23HA0068 | May 11, 2023 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEMS - STA. FILOMENA SHORE PROTECTION - STA. FILOMENA, ALBURQUERQUE, BOHOL | Completed | ₱17.5M |
| 23HA0032 | Feb 16, 2023 | CONSTRUCTION OF ROAD, ALBURQUERQUE, BOHOL | Completed | ₱4.9M |
| 22HA0182 | Dec 16, 2022 | CONSTRUCTION OF 1STY-2CL, TAGBUANE ES, ALBURQUERQUE, BOHOL | Completed | ₱7.3M |
| 22HA0156 | Oct 5, 2022 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0248+000 - K0249+680 | Completed | ₱40.1M |