Project 21HA0157
DPWH infrastructure contract
Contract ID:
21HA0157
Fingerprint:
911afe084a1fdf…a179cf13d0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 11, 2021 (5 yrs 5 mo ago) · Target/actual end Jul 23, 2021
Description:
REHABILITATION (RENOVATION) OF MULTI-PURPOSE BUILDING (HEALTH CENTER), BARANGAY SAN ISIDRO, TAGBILARAN CITY, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R · DPWH contractor code 22901
Contract amount:
₱994,983.44 (₱995.0K)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0074 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | Completed | ₱9.9M |
| 25HA0084 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY MANSASA, TAGBILARAN CITY, BOHOL | Completed | ₱4.8M |
| 25HA0092 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BRGY. UBUJAN, TAGBILARAN CITY, BOHOL | On-Going | ₱4.9M |
| 25HA0100 | Jun 2, 2025 | CONSTRUCTION OF ROAD AT MAGSAYSAY ST., BRGY. MANGA, TAGBILARAN, BOHOL | Completed | ₱8.9M |
| 24HA0176 | May 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | On-Going | ₱2.4M |
| 24HA0178 | May 30, 2025 | CONSTRUCTION OF DRAINAGE SYSTEM ALONG TAGBILARAN CITY EAST ES AND TAGBILARAN CITY CENTRAL ES, TAGBILARAN CITY, BOHOL | Completed | ₱4.8M |
| 25HA0067 | May 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER) AT CAMP FRANCISCO DAGOHOY, TAGBILARAN CITY, BOHOL | On-Going | ₱4.9M |
| 25HA0069 | May 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDINGS (DAMPAS E/S, 702ND COMMUNITY DEFENSE CENTER INCLUDING RELATED FACILITIES, CAMP BERNIDO, DAO, TAGBILARAN CITY, BOHOL | On-Going | ₱5.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.