Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21I00019

DPWH infrastructure contract
Contract ID:
21I00019
Fingerprint:
db17a46bb4ad9c…85cdde72ab Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 22, 2021 (5 yrs 8 mo ago) · Target/actual end Mar 29, 2022
Description:
NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - JARO - RUBAS - ORMOC ROAD (JARO SIDE), LEYTE, LEYTE 2ND LD
Category:
Bridges: Construction - Concrete (Superstructure) - with Cast-in-Place Piles, Roads: Construction - PCCP
Implementing office:
DPWH Region VIII · Region VIII
Contract amount:
₱83,194,862.23 (₱83.2M)
Funding source:
Regular Infra - Bridges: Construction - Concrete (Superstructure) - with Cast-in-Place Piles, Roads: Construction - PCCP
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ID0066Apr 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 1, JARO,LEYTECompleted₱5.9M
25ID0033Apr 7, 2025CONSTRUCTION OF ROAD,BARANGAY LA PAZ,JARO,LEYTEOn-Going₱14.5M
25ID0021Apr 4, 2025CONSTRUCTION OF ROAD,BARANGAY ANIBONGON, JARO,LEYTEOn-Going₱5.2M
25ID0034Apr 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VILLA PAZ,JARO,LEYTECompleted₱7.9M
25ID0032Apr 3, 2025CONSTRUCTION OF ROAD, BARANGAY ATIPOLO,JARO,LEYTEOn-Going₱19.8M
25ID0012Mar 24, 2025CONSTRUCTION OF ROAD, SITIO SOLEDAD, BARANGAY SANTO NIÑO, JARO, LEYTECompleted₱9.9M
25ID0027Mar 20, 2025CONSTRUCTION OF ROAD,BARANGAY SAN ROQUE,JARO,LEYTECompleted₱16.0M
25ID0028Mar 20, 2025CONSTRUCTION OF ROAD,SITIO MAITOM,BARANGAY SAN AGUSTIN, JARO,LEYTEOn-Going₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.