Project 21IB0016
DPWH infrastructure contract
Contract ID:
21IB0016
Fingerprint:
6abde0e54aabdb…e305ef421f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 15, 2021 (5 yrs 8 mo ago) · Target/actual end Mar 16, 2021
Description:
REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE BOBLARAN BR. (B00534SM) ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD, EASTERN SAMAR
Category:
Bridges
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
TWO-BROTHERS CONSTRUCTION · DPWH contractor code 45485
Contract amount:
₱966,405.20 (₱966.4K)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0075 | Dec 8, 2025 | CONSTRUCTION OF ROAD (SEASIDE), BARANGAY GARDEN, ARTECHE, EASTERN SAMAR | On-Going | ₱4.8M |
| 25I00115 | Apr 10, 2025 | BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CAGPILE TO BARANGAY BATO, ORAS AND ARTECHE | On-Going | ₱14.8M |
| 25IB0033 | Feb 25, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0964+705 - K0964+720 | Completed | ₱2.2M |
| 25IB0034 | Feb 25, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0964+971 - K0964+983 | Completed | ₱2.2M |
| 24I00202 | Jul 5, 2024 | SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BARANGAY TEBALAWON TO BARANGAY TAWAGAN, ARTECHE, EASTERN SAMAR | On-Going | ₱45.3M |
| 24I00205 | Jul 5, 2024 | SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD BRGY. BIGO, SITIO KABAY-ANGAN TO BRGY. CONCEPTION TO BRGY. CAGSALAY, ARTECHE, EASTERN SAMAR | On-Going | ₱48.2M |
| 24IB0120 | Jun 17, 2024 | CONSTRUCTION OF ACADEMIC BUILDING EASTERN SAMAR STATE UNIVERSITY, ARTECHE CAMPUS, ARTECHE, EASTERN SAMAR | Completed | ₱20.5M |
| 24IB0097 | Jun 3, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING ARTECHE CAMPUS OF EASTERN SAMAR STATE UNIVERSITY, EASTERN SAMAR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.