Project 21IB0067
DPWH infrastructure contract
Contract ID:
21IB0067
Fingerprint:
4c9947b0c08fd4…21e029b7f3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2021 (5 yrs 8 mo ago) · Target/actual end Apr 3, 2021
Description:
REHABIITATION OF ROAD, BARANGAY 3, SAN JULIAN, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
TUBIGAN BUILDERS · DPWH contractor code 33185
Contract amount:
₱4,949,913.35 (₱4.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4a6465e91386… | Jan 29, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱4,876,892.02 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0153 | Nov 12, 2025 | CONSTRUCTION OF ROAD, BARANGAY LIBAS, SAN JULIAN, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0025 | Feb 25, 2025 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, WRIGHT-TAFT-BORONGAN ROAD, K0919+052 - K0920+085 | Completed | ₱8.5M |
| 24IB0056 | Apr 11, 2024 | CONSTRUCTION OF POLO UNO ROAD, BARANGAY PUTONG, SAN JULIAN, EASTERN SAMAR | Completed | ₱6.9M |
| 24IB0038 | Mar 18, 2024 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, LAYOG BR. (B00567SM), ALONG WRIGHT-TAFT-BORONGAN RD | Completed | ₱9.8M |
| 23IB0122 | Aug 10, 2023 | CONSTRUCTION OF 1STY2CL, PAGBABANGNAN ELEMENTARY SCHOOL, SAN JULIAN, EASTERN SAMAR | Completed | ₱5.0M |
| 23IB0120 | Aug 8, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.7M |
| 23IB0102 | Jun 14, 2023 | CONSTRUCTION OF ROAD, CASOROY - LAYOG, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.8M |
| 23IB0104 | Jun 14, 2023 | CONSTRUCTION OF ACCESS ROAD, BARANGAY PUTONG TO BARANGAY LIBAS, SITIO MACAARONGON, BARANGAY LIBAS, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.