Project 21IB0088
DPWH infrastructure contract
Contract ID:
21IB0088
Fingerprint:
e964a6a5450704…524a3f1086 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 7, 2021 (5 yrs 1 mo ago) · Target/actual end Feb 9, 2022
Description:
CONSTRUCTION OF ROAD, BARANGAY PALAMRAG MERCEDES TO BARANGAY ALINGAROG, GUIUAN, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
DRAGON CONSTRUCTION · DPWH contractor code 48354
Contract amount:
₱9,799,999.10 (₱9.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9e7e5cdf0007… | Sep 23, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱9,682,508.89 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0129 | Aug 14, 2025 | CONCRETING OF BRGY. 02 POBLACION TO BRGY. SAN ROQUE TO BRGY. BANUYO FMR, BRGY. 02 POBLACION, SAN ROQUE AND BANUYO, MERCEDES, EASTERN SAMAR | On-Going | ₱5.0M |
| 24IB0094 | Jun 3, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN JOSE ELEMENTARY SCHOOL, BARANGAY SAN JOSE, MERCEDES, EASTERN SAMAR | Completed | ₱5.0M |
| 24IB0001 | Feb 13, 2024 | CONSTRUCTION OF ROAD, BARANGAY BUYAYAWON TO BARANGAY 4, MERCEDES, EASTERN SAMAR | On-Going | ₱9.7M |
| 23IB0095 | Aug 3, 2023 | CONCRETING OF BRGY. SUNG-AN TO BRGY. BUSAY TO POBLACION 1 FMR, MERCEDES, EASTERN SAMAR | Completed | ₱19.9M |
| 23IB0116 | Aug 3, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, MERCEDES, EASTERN SAMAR | Completed | ₱9.8M |
| 23IB0057 | Mar 22, 2023 | CONSTRUCTION OF ROAD, BARANGAY CAMBANTE - BARANGAY BUSAY, MERCEDES, EASTERN SAMAR | Completed | ₱9.9M |
| 22IB0150 | Jan 16, 2023 | CONSTRUCTION OF 1STY2CL, BUSAY PRIMARY SCHOOL, MERCEDES, EASTERN SAMAR | Completed | ₱6.5M |
| 22IB0078 | Apr 7, 2022 | CONSTRUCTION OF BARANGAY ROAD AT BARANGAY SUNG-AN, BARANGAY CAGBUNGA AND BARANGAY BOBON, MERCEDES, EASTERN SAMAR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.