Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21ID0011

DPWH infrastructure contract
Contract ID:
21ID0011
Fingerprint:
fc16db17a2fec8…728d484caa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 14, 2021 (5 yrs 7 mo ago) · Target/actual end Sep 10, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) MAYORGA NHS,MAYORGA,LEYTE
Category:
Buildings and Facilities
Implementing office:
DPWH Leyte 2nd DEO · Region VIII
Contractor:
VENUS ENGINEERING AND CONSTRUCTION · DPWH contractor code 33614
As listed: VENUS ENGINEERING & CONSTRUCTION
Contract amount:
₱5,847,187.74 (₱5.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
82a620499062…Mar 22, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 2ND DEO₱5,847,187.74

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26ID0029Sep 11, 2026CONSTRUCTION OF CONCRETE ROAD, CHAINAGE 1+880 -CHAINAGE 2+680, SITIO BANHAWAY-BARANGAY DOYOG,LA PAZ BARANGAY BURGOS,MAYORGA ROAD,LEYTEOn-Going₱9.6M
25ID0069Apr 15, 2025CONSTRUCTION OF LIBERTY BRIDGE,BARANGAY LIBERTY,MAYORGA,LEYTEOn-Going₱29.3M
25ID0044Mar 26, 2025CONSTRUCTION OF CONCRETE ROAD,BRGY. A. BONIFACIO-BARANGAY CAMANSI,MAYORGA,LEYTEOn-Going₱19.5M
25ID0047Mar 25, 2025CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF HIBUGA FLOOD CONTROL STRUCTURE AND DRAINAGE, HIBUGA RIVER BASIN(DOWNSTREAM),BARANGAY LIBERTY, MAYORGA,LEYTECompleted₱96.4M
25ID0052Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD, SITIO BANHAWAY-BARANGAY DOYOG,LA PAZ-BARANGAY BURGOS,MAYORGA ROAD,LEYTE, MAYORGA AND LA PAZ,LEYTECompleted₱19.6M
25ID0043Mar 21, 2025CONSTRUCTION OF CONCRETE ROAD,POBLACION ZONE 1-BARANGAY SAN ROQUE,MAYORGA,LEYTECompleted₱4.9M
25ID0053Mar 21, 2025CONSTRUCTION OF CONCRETE ROAD,BARANGAY A. BONIFACIO-BARANGAY BURGOS, MAYORGA,LEYTECompleted₱14.7M
25ID0003Mar 17, 2025ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE TERTIARY ROADS MAYORGA-LA PAZ ROAD K0946+(-043.00)-K0946+385.00,MAYORGA,LEYTECompleted₱17.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.