Project 21IF0088
DPWH infrastructure contract
Contract ID:
21IF0088
Fingerprint:
5126760b29623b…f910ae066d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 10, 2021 (5 yrs ago) · Target/actual end Jun 7, 2022
Description:
CONSTRUCTION OF ALBUERA SEAWALL, ALBUERA, LEYTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
A.C. RIVERO DEVELOPMENT CORPORATION · DPWH contractor code 5122
Contract amount:
₱48,509,929.42 (₱48.5M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7e27144ab90e… | Oct 26, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 4TH DEO | ₱46,549,647.12 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IF0039 | Aug 10, 2026 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ORMOC-BAYBAY- SOUTHERN LEYTE BDRY. RD. - K1034+082 - K1034+265, K1034+340 - K1034+806 | On-Going | ₱41.2M |
| 26IF0033 | Jul 27, 2026 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ORMOC-BAYBAY-SOUTHERN LEYTE BDRY. RD. - K1035+045 - K1035+510, K1037+124 - K1037+246 | On-Going | ₱31.3M |
| 25IF0097 | Aug 27, 2025 | CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS), SALVACION ELEMENTARY SCHOOL, BRGY. SALVACION, ALBUERA, LEYTE; DOÑA MARIA ELEMENTARY SCHOOL, BRGY. DOÑA MARIA, ALBUERA, LEYTE; ALBUERA SOUTH CENTRAL SCHOOL, BRGY. DAMULAAN, ALBUERA, LEYTE; | Completed | ₱2.6M |
| 25IF0093 | Aug 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DAMULAAN, ALBUERA, LEYTE | Completed | ₱4.9M |
| 25IF0014 | Mar 26, 2025 | CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE CAGBULO RIVER, ALBUERA, LEYTE | Completed | ₱48.1M |
| 25IF0047 | Mar 19, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE- PRIMARY ROADS - ORMOC - BAYBAY - SOUTHERN LEYTE BDRY RD - K1031+785 - K1032+129 | Completed | ₱21.2M |
| 25IF0069 | Mar 19, 2025 | CONSTRUCTION OF ROAD, POBLACION, ALBUERA, LEYTE | Completed | ₱18.6M |
| 25IF0057 | Mar 4, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG ALBUERA-DIVERSION ROAD, ALBUERA, LEYTE | Completed | ₱48.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.