Physical progress:
100%
Timeline:
Start Feb 15, 2021 (5 yrs 8 mo ago) · Target/actual end Nov 2, 2021
Description:
CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF DINAS RIVER FLOOD CONTROL, BRGY. BALONGATING, GUIPOS, ZAMBOANGA DEL SUR (PHASE II)
Category:
Flood Control and Drainage
Implementing office:
DPWH Zamboanga del Sur 2nd DEO · Region IX
Contractor:
JIMWEN CONSTRUCTION AND GENERAL MERCHANDISE · DPWH contractor code 33066
As listed: JIMWEN CONSTRUCTION & GENERAL MERCHANDISE
Contract amount:
₱27,127,704.22 (₱27.1M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f11e24260f56… | Jan 28, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL SUR | ₱27,127,704.22 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JG0043 | Mar 28, 2025 | CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO COMPOUND, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱39.2M |
| 25JG0041 | Mar 20, 2025 | CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO MAIN BUILDING, PUROK 1B, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱11.7M |
| 25JG0039 | Mar 13, 2025 | CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO COVERED COURT, GUIPOS, ZAMBOANGA DEL SUR | Completed | ₱4.9M |
| 25JG0040 | Mar 13, 2025 | CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO STAFF HOUSE, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱53.8M |
| 25JG0001 | Feb 19, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS ROAD AND DIVERSION ROADS ALONG NRJ POBLACION GUIPOS - LINTUM, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱29.3M |
| 25JG0032 | Feb 19, 2025 | NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - ALONG JCT DUMALINAO-MARGOSATUBIG RD - K1685 + 140 - K1685 + 354, BALONGATING, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱7.3M |
| 25JG0035 | Feb 19, 2025 | ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT. DUMALINAO-MARGOSATUBIG RD K1689 + 190 - K1689 + 265, GUIPOS, ZAMBOANGA DEL SUR | On-Going | ₱29.3M |
| 24JG0051 | Jun 17, 2024 | CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO MAIN BUILDING, PUROK 1B, BRGY. POBLACION, GUIPOS, ZAMBOANGA DEL SUR | Completed | ₱49.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.