Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21K00057

DPWH infrastructure contract
Contract ID:
21K00057
Fingerprint:
dbdffa63acd8b7…74fb36a5d4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 14, 2021 (5 yrs 6 mo ago) · Target/actual end Jun 30, 2023
Description:
CONST. OF BYPASS & DIVERSION ROADS, CDOC-ILIGAN HINTERLAND ROAD(JCT.CDO-KIBARITAN ROAD/DANSOLIHON-JC
Category:
Roads
Implementing office:
DPWH Region X · Region X
Contract amount:
₱91,223,688.61 (₱91.2M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KL0124May 28, 2025CONSTRUCTION OF CARABAO VALLEY ROAD, BARANGAY AWANG, OPOL, MISAMIS ORIENTALOn-Going₱48.5M
25K00362May 26, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS OPOL DIVERSION ROAD (OPOL-CANITO-AN), PACKAGE 18, MISAMIS ORIENTALOn-Going₱47.8M
25KL0129May 26, 2025CONSTRUCTION OF BRIDGE, SITIO PIGTAO, BARANGAY NANGCAON, OPOL, MISAMIS ORIENTALOn-Going₱96.0M
25KL0110May 23, 2025CONCRETING OF ZONE 4-MALAORO ROAD, BARANGAY MALANANG, OPOL, MISAMIS ORIENTALOn-Going₱49.0M
25KL0113May 23, 2025CONCRETING OF BINIGWAYAN-MALAORO ROAD, BARANGAY MALANANG, OPOL, MISAMIS ORIENTALOn-Going₱48.6M
25KL0117May 23, 2025CONSTRUCTION OF DRAINAGE, BARANGAY POBLACION AND BARANGAY TABOC, OPOL, MISAMIS ORIENTALOn-Going₱48.6M
25KL0006Mar 19, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY BONBON, OPOL MISAMIS ORIENTALOn-Going₱4.9M
25KL0017Mar 19, 2025CONSTRUCTION OF PEDESTRIAN OVERPASS ALONG BCIR-K1448+420, BRGY. LUYONG BONBON, OPOL, MISAMIS ORIENTALOn-Going₱19.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.