Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21KC0108

DPWH infrastructure contract
Contract ID:
21KC0108
Fingerprint:
16937b1f213428…8eeeae5735 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 12, 2021 (5 yrs 4 mo ago) · Target/actual end Feb 15, 2022
Description:
CONCRETING OF SITIO SAN ROQUE TO SITIO TAGULILONG, BRGY. CONCEPCION FMR, BRGY. CONCEPCION, PANGANTUCAN, BUKIDNON
Category:
Roads
Implementing office:
Contract amount:
₱11,940,000.00 (₱11.9M)
Funding source:
Outside Infra - GAA 2021 DA FMR
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00229May 26, 2025CONSTRUCTION OF ROAD, FROM THE NATIONAL HIGHWAY TO LUMAGWAS-KIDANGGIN ROAD LEADING TO HOT SPRINGS, PANGANTUCAN, BUKIDNONOn-Going₱95.5M
25KN0057May 23, 2025CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM (RWCS) IN PUBLIC FACILITIES:Completed₱2.5M
25K00312Apr 7, 2025CONSTRUCTION OF JCT. CAMP KIBARITAN-PANGANTUCAN - JCT GUINOYURAN-VALENCIA ROAD, PANGANTUCAN SECTION, PACKAGE 5, BUKIDNONOn-Going₱189.1M
25K00267Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 3, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00268Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00269Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00270Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 5, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25KN0015Mar 26, 2025REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS, MARAMAG - MARADUGAO RD - K1588 + 054 - K1588 + 157Completed₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.