Completed
Physical progress:
100%
Timeline:
Start Mar 28, 2022 (4 yrs 7 mo ago) · Target/actual end Aug 19, 2022
Description:
COMPLETION OF LEGISLATIVE BUILDING, SANGGUNIANG PANLALAWIGAN, PROVINCIAL CAPITOL, BRGY. CABIDIANAN, MUNICIPALITY OF NABUNTURAN, PROVINCE OF DAVAO DE ORO
Category:
Buildings and Facilities
Implementing office:
Contractor:
PMMGS CONSTRUCTION CORPORATION · DPWH contractor code 43121
Contract amount:
₱9,899,342.27 (₱9.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
17605391434d…Mar 21, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - COMPOSTELA VALLEY₱9,849,846.27

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26LC0037Jul 9, 2026NABUNTURAN-LAAK ROAD, BARANGAY SANTA FE (STA.6+429.650 + STA. 6+505.65), NEW CORELLA, DAVAO DEL NORTEOn-Going₱94.4M
25LA0068Sep 3, 2025CONSTRUCTION (COMPLETION) OF ADMINISTRATIVE BUILDING, DAVAO DE ORO 1ST DEO, NABUNTURAN, DAVAO DE OROOn-Going₱19.6M
25LA0079Sep 3, 2025CONSTRUCTION OF ROAD, BARANGAY MAINIT-PANARAON, MACO, DAVAO DE OROOn-Going₱48.0M
25LA0098Sep 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DAUIS, NABUNTURAN, DAVAO DE OROOn-Going₱5.9M
25LA0077Jul 28, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY KAO ELEMENTARY SCHOOL, NABUNTURAN, DAVAO DE OROOn-Going₱2.9M
25LA0088Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, HALL OF JUSTICE, BARANGAY CABIDIANAN, NABUNTURAN, DAVAO DE OROOn-Going₱34.6M
25LA0091Jul 28, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY LIBASAN ELEMENTARY SCHOOL, NABUNTURAN, DAVAO DE OROOn-Going₱3.9M
25LA0078Jul 8, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY KAO NATIONAL HIGH SCHOOL, NABUNTURAN, DAVAO DE OROCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.