Project 21LG0007

DPWH infrastructure contract
Contract ID:
21LG0007
Fingerprint:
bd510f0fdbe84d…2fb297ed55 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2021 (5 yrs 8 mo ago) · Target/actual end Sep 27, 2021
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAMOGNA RIVER , GOVERNOR GENEROSO , DAVAO ORIENTAL
Category:
Flood Control and Drainage
Implementing office:
Contractor:
RITCHE-NATHALIE BUILDERS AND GENERAL MERCHANDISE · DPWH contractor code 27501
As listed: RITCHE-NATHALIE BUILDERS & GENERAL MERCHANDISE
Contract amount:
₱19,207,914.59 (₱19.2M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
695576ecada8…Feb 9, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO ORIENTAL 2ND₱19,207,914.59

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25L00092Jul 4, 2025CONSTRUCTION OF CONCRETE ROAD - UPPER TIBANBAN - OREGON - MAGDUG ROAD, PACKAGE 4, DAVAO ORIENTALOn-Going₱72.6M
25LG0023Mar 30, 2025ROAD WIDENING (2-4 LANES)-TIBANBAN-LAVIGAN RD- K1796 +000 - K1796 + 347, K1796 +387- K1796 +940On-Going₱39.0M
25LG0057Mar 27, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG LAVIGAN, GOVERNOR GENEROSO, DAVAO ORIENTALOn-Going₱48.3M
25LG0061Mar 27, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PACKAGE 2, GOVERNOR GENEROSO, DAVAO ORIENTALOn-Going₱4.9M
25LG0067Mar 27, 2025REHABILITATION OF MULTI- PURPOSE BUILDING, GOVERNOR GENEROSO, DAVAO ORIENTALOn-Going₱8.9M
25LG0030Mar 26, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG TIBANBAN-LAVIGAN RD- K1773+ (-754)-K1829+862On-Going₱95.5M
25LG0022Mar 20, 2025ROAD WIDENING (2-4 LANES) -TIBANBAN-LAVIGAN RD- K1794 + 892 - K1796 + 000On-Going₱38.8M
25LG0047Mar 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PACKAGE 1, GOVERNOR GENEROSO, DAVAO ORIENTALOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.