Project 21MB0084
DPWH infrastructure contract
Contract ID:
21MB0084
Fingerprint:
27b78339219d74…4538edab1c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 29, 2021 (5 yrs 7 mo ago) · Target/actual end Jul 7, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH) AT BARANGAY PULABATO, TAMPAKAN, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH South Cotabato 1st DEO · Region XII
Contractor:
LTB BUILDERS & CONSTRUCTION · DPWH contractor code 18752
Contract amount:
₱3,959,967.30 (₱4.0M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d392b9d5a16b… | Mar 26, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1S | ₱3,801,516.68 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MB0076 | Jul 18, 2025 | REHABILITATION (COMPLETION) OF IP'S WATER SUPPLY SYSTEM, PUROK GUMAMELA, BARANGAY PULABATO, TAMPAKAN, SOUTH COTABATO | Completed | ₱2.4M |
| 25MB0061 | Mar 11, 2025 | CONSTRUCTION OF ROAD, PUROK ANTHURIUM, BARANGAY BUTO, TAMPAKAN, SOUTH COTABATO | Completed | ₱4.9M |
| 25MB0062 | Mar 11, 2025 | CONSTRUCTION OF ROAD, PUROK SANTOS, BARANGAY KIPALBIG, TAMPAKAN, SOUTH COTABATO | Completed | ₱4.9M |
| 25MB0063 | Mar 11, 2025 | CONSTRUCTION OF ROAD OF AGAPAY CANICO ROAD, BARANGAY POBLACION, TAMPAKAN, SOUTH COTABATO | Completed | ₱4.9M |
| 24M00223 | Mar 4, 2025 | CONSTRUCTIONS OF RIVER BANK PROTECTION WITH ESPLANADE ALONG ALTAYAN RIVER, STA 0+000 - STA 0+200; STA 0+000 - STA 0+160.473, BRGY. PULABATO, PULABATO, TAMPAKAN, SOUTH COTABATO | On-Going | ₱48.8M |
| 24MB0092 | Jul 30, 2024 | CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING IN LAMBAYONG INTEGRATED SCHOOL, BRGY. LAMBAYONG, TAMPAKAN, SOUTH COTABATO | Completed | ₱5.0M |
| 24MF0061 | Jul 4, 2024 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) MAUNO E/S, COLUMBIO, SULTAN KUDARAT, CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) SAL-NAONG E/S, COLUMBIO, SULTAN KUDARAT, CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) LIMONZO E/S, COLUMBIO, SULT | Completed | ₱2.9M |
| 24M00133 | May 17, 2024 | CONSTRUCTION OF ROAD, STA. 0+000 - STA. 0+209.50, BARANGAY DANLAG, TAMPAKAN, SOUTH COTABATO | Completed | ₱4.9M |