Physical progress:
100%
Timeline:
Start Mar 23, 2021 (5 yrs 7 mo ago) · Target/actual end Dec 20, 2021
Description:
CONSTRUCTION OF CONCRETE ROAD ALONG JCT. DAVAO-COTABATO (CROSSING BAGUER)-SITIO DALUMANGKOM-SITIO LAMPAKI ROAD, ALAMADA, NORTH COTABATO
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
LLABAN CONSTRUCTION & SUPPLY (FORMERLY: LLABAN CON · DPWH contractor code 29504
Contract amount:
₱95,528,284.72 (₱95.5M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MD0044 | Jul 28, 2025 | CONSTRUCTION OF ROAD, SITIO PINAMULAAN - BARANGAY NORTH MANUANGAN - BARANGAY SOUTH MANUANGAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0059 | Jul 7, 2025 | JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATO | Completed | ₱65.5M |
| 25MD0012 | Mar 6, 2025 | CONSTRUCTION OF ROAD JCT. HIGHWAY - BULUAN ROAD, BARANGAY BULUAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0030 | Mar 6, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CAPAYURAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0031 | Feb 27, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱94.7M |
| 25MD0038 | Feb 27, 2025 | CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATO | Completed | ₱94.4M |
| 24MD0066 | May 15, 2024 | CONCRETING OF BRGY. MALU-AU TO BRGY. NEW CULASI FMR, BRGY. MALU-AU AND BRGY. NEW CULASI, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
| 24MD0075 | May 15, 2024 | CONCRETING OF BRGY. BALOGO TO SITIO PAGLAUM FMR, BRGY. BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.