Project 21ME0060

DPWH infrastructure contract
Contract ID:
21ME0060
Fingerprint:
3608f3fb25c828…4fbf538456 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 19, 2021 (5 yrs 6 mo ago) · Target/actual end Oct 14, 2021
Description:
CONSTRUCTION OF WATER SYSTEM (LEVEL II), (SITIO TALIFARA), BRGY. ALGRIA
Category:
Water Provision and Storage
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
HANNA VIA CONSTRUCTION, INC. · DPWH contractor code 32887
As listed: HANNA VIA CONSTRUCTION, INC. (FORMERLY:HANNA VIA DESIGN & CONSTRUCTION)
Contract amount:
₱2,797,443.17 (₱2.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d5d93ae1fb50…Mar 29, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SARANGANI DISTRICT E₱279,744.17

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ME0109Sep 19, 2025CONSTRUCTION OF KAWAS WATER SYSTEM, KAWAS, ALABEL, SARANGANI PROVINCECompleted₱4.2M
25ME0125Sep 19, 2025CONSTRUCTION (COMPLETION) OF DPWH SARANGANI DISTRICT ENGINEERING OFFICE BUILDING, ALABEL, SARANGANI PROVINCECompleted₱83.3M
25ME0113Aug 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, (CULTURAL AND TOURISM CENTER-PHASE II), CAPITOL COMPOUND, ALABEL, SARANGANI PROVINCECompleted₱19.8M
25M00018Aug 4, 2025CONSTRUCTION OF LADOL FLOOD MITIGATION STRUCTURE, ALABEL, SARANGANICompleted₱96.0M
25ME0086Jul 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) AT LATIAN ELEMENTARY SCHOOL, UPPER LATIAN, BARANGAY DOMOLOK, ALABEL, SARANGANI PROVINCECompleted₱4.9M
25ME0087Jul 30, 2025CONCRETING OF TOKAWAL TO PALAO VILLAGE ROAD, TOKAWAL, ALABEL, SARANGANI PROVINCECompleted₱4.7M
25ME0093Jul 30, 2025CONSTRUCTION OF BARANGAY BALUNTAY TO SITIO LAMLABONG ROAD, ALABEL, SARANGANI PROVINCECompleted₱48.8M
25ME0095Jul 30, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE PROTECTING NATIONAL HIGHWAY FROM SACI TO PROVINCIAL CAPITOL TO MOLO CREEK, ALABEL, SARANGANI PROVINCEOn-Going₱77.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.