Project 21MI0100
DPWH infrastructure contract
Contract ID:
21MI0100
Fingerprint:
84a3e603e1b9a2…b9f2e9283e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 13, 2021 (5 yrs 2 mo ago) · Target/actual end Feb 28, 2022
Description:
CONCRETING OF PUROK 2 TO PUROK 5, BRGY. DAIG FMR, BRGY. DAIG, TULUNAN, NORTH COTABATO
Category:
Roads
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contractor:
COFEJOK CONSTRUCTION AND SUPPLY CORPORATION (FORME · DPWH contractor code 27493
Contract amount:
₱12,073,093.14 (₱12.1M)
Funding source:
Outside Infra - GAA 2021 DA FMR
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MC0011 | Jun 17, 2026 | ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1594 + (-807) - K1594 + (-232) | On-Going | ₱16.8M |
| 25LD0160 | Jul 22, 2025 | CONSTRUCTION OF CONCRETE ROAD, BARANGAY POB.-MALANO-BOB-BRGY. BARAYONG-BALA, MAGSAYSAY, DAVAO DEL SUR | On-Going | ₱122.5M |
| 25LD0166 | Jul 22, 2025 | CONSTRUCTION OF ROAD, SITIO TALAMBATO, BARANGAY ASBANG TO BARANGAY ASINAN, MATANAO, DAVAO DEL SUR | On-Going | ₱140.4M |
| 25LD0167 | Jul 22, 2025 | CONSTRUCTION OF ROAD, BARANGAY TACUL- BARANGAY UPPER BALA, MAGSAYSAY, DAVAO DEL SUR | On-Going | ₱109.9M |
| 25LD0153 | Jun 9, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-REVETMENT ALONG BALATUKAN RIVER (MAGSAYSAY BRIDGE UPSTREAM & DOWNSTREAM SECTION, PHASE 1), MAGSAYSAY, DAVAO DEL SUR | On-Going | ₱98.5M |
| 25LD0103 | Mar 24, 2025 | ROAD WIDENING- DAVAO- COTABATO RD (JCT. DIGOS- COTABATO SECT)- K1587+422- K1588+220, DAVAO DEL SUR | Completed | ₱32.8M |
| 25LD0012 | Mar 14, 2025 | CONSTRUCTION OF CONCRETE ROAD- BACUNGAN- MALAWANIT ROAD IN SUPPORT OF CACAO INDUSTRY, MAGSAYSAY, DAVAO DEL SUR | On-Going | ₱9.8M |
| 25LD0032 | Mar 14, 2025 | ROAD WIDENING- DAVAO- COTABATO RD (JCT DIGOS- COTABATO SECT)- K1590+000-K1590+704, DAVAO DEL SUR | Completed | ₱28.4M |