Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21NA0022

DPWH infrastructure contract
Contract ID:
21NA0022
Fingerprint:
a292b2c169a1b9…54e8a01d82 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 27, 2021 (5 yrs 5 mo ago) · Target/actual end Sep 1, 2021
Description:
READ - CONCRETING OF ROAD, BALEGUIAN, JABONGA, AGUSAN DEL NORTE
Category:
Roads
Implementing office:
Contract amount:
₱9,799,994.69 (₱9.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24N00229Jul 17, 2025CONSTRUCTION OF EVACUATION CENTEROn-Going₱43.4M
25NA0021Mar 24, 2025CONSTRUCTION OF ROAD, COLORADO-CORO, BARANGAY COLORADO, JABONGA, AGUSAN DEL NORTECompleted₱29.7M
25NA0022Mar 24, 2025CONSTRUCTION OF SABO DAM ALONG BALEGUIAN CREEK, MARAIGUING CIS, JABONGA, AGUSAN DEL NORTECompleted₱14.6M
25NA0036Mar 24, 2025CONCRETING OF BRGY. SAN VICENTE TO TOP BRIDGE FMR (PHASE I), BRGY. SAN VICENTE, JABONGA, AGUSAN DEL NORTEOn-Going₱44.7M
25N00046Feb 21, 2025MAHARLIKA HIGHWAY (SURIGAO-AGUSAN SECT)- K1188+748-K1190+000On-Going₱29.7M
25N00047Feb 21, 2025MAHARLIKA HIGHWAY (SURIGAO-AGUSAN SECT)- K1187+400-K1188+540On-Going₱56.9M
24NA0037Jun 13, 2024CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. POBLACION, JABONGA, AGUSAN DEL NORTECompleted₱3.0M
24N00135May 13, 2024CONSTRUCTION OF DIKE WITH CONCRETE REVETMENT ALONG PUYO RIVER, DOWNSTREAM SECTION ALONG ABUTMENT B OF THE BRIDGE, PACKAGE 1, JABONGA, AGUSAN DEL NORTECompleted₱193.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.