Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21NA0024

DPWH infrastructure contract
Contract ID:
21NA0024
Fingerprint:
89738c67abf8c6…13116db47f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 24, 2021 (5 yrs 5 mo ago) · Target/actual end Sep 27, 2021
Description:
ROAD WIDENING-TERTIARY-PANDANON-MAGALLANES ROAD K1219+785.50 - K1220+000, K1221+450 - K1222+120 MAGALLANES, AGUSAN DEL NORTE
Category:
Roads
Implementing office:
Contractor:
REGERYS CONSTRUCTION & SUPPLY · DPWH contractor code 44367
As listed: REGERYS CONSTRUCTION AND SUPPLY
Contract amount:
₱19,325,947.04 (₱19.3M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
8d1a27d4268f…May 5, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AGUSAN DEL NORTE D₱19,325,947.04

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25N00152May 19, 2025BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTEOn-Going₱14.4M
25NA0002Mar 24, 2025CONSTRUCTION OF ROAD ALONG SEAWALL DIKE FROM BARANGAY SANTO ROSARIO TO BARANGAY SANTO NINO, MAGALLANES, AGUSAN DEL NORTECompleted₱9.9M
25N00116Feb 21, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT LOWER AGUSAN RIVER, MAGALLANES PAGATPATAN SECTION, MAGALLANES, AGUSAN DEL NORTECompleted₱286.0M
25N00192Feb 21, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE PROTECTING ABUTMENT OF BANZA BRIDGE 3 ALONG BANZA-MAGALLANES ROAD, PACKAGE 2, AGUSAN DEL NORTECompleted₱143.8M
25NA0019Feb 13, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CALOC-AN ELEMENTARY SCHOOL, BARANGAY CALOC-AN, MAGALLANES, AGUSAN DEL NORTECompleted₱4.9M
24N00069Oct 17, 2024BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTECompleted₱147.2M
24N00070Oct 17, 2024BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTE, PACKAGE IICompleted₱96.5M
24NA0011Feb 21, 2024CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE , LA FORTUNA, BARANGAY BUHANG, MAGALLANES, AGUSAN DEL NORTECompleted₱96.4M