FY2026 GAA: ₱6.79T
PisoScan

Project 21NA0048

DPWH infrastructure contract
Contract ID:
21NA0048
Fingerprint:
011456ca285a9a…dfc3cc15d7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 14, 2021 (5 yrs 5 mo ago) · Target/actual end Dec 30, 2021
Description:
CONSTRUCTION OF BRGY. LINGAYAO-INTERIM BRGY. OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPIT, CARMEN (LASBUENASCAR) SUSTAINABLE AGRO-FORESTY DEVELOPMENT PROJECT (PACKAGE 1), LAS NIEVES, AGUSAN DEL NORTE
Category:
Roads
Implementing office:
Contractor:
EQUI-PARCO CONSTRUCTION COMPANY · DPWH contractor code 14332
Contract amount:
₱60,793,574.93 (₱60.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3575cdcf507a…May 20, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AGUSAN DEL NORTE D₱60,164,021.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ND0027Aug 7, 2025COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT WITH BLEACHERS), BARANGAY LAWAN-LAWAN, LAS NIEVES, AGUSAN DEL NORTECompleted₱6.9M
25ND0131Aug 7, 2025COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TINUCORAN, LAS NIEVES, AGUSAN DEL NORTECompleted₱6.8M
25ND0071Jul 18, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT LAS NIEVES NATIONAL HIGH SCHOOL BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTEOn-Going₱9.9M
25N00099Apr 10, 2025AGUSAN DEL NORTE/AGUSAN DEL SUR NORTH-SOUTH LATERAL ROAD, (LAS NIEVES, AGUSAN DEL NORTE - KAPALONG, DAVAO DEL NORTE), LAS NIEVESOn-Going₱48.1M
25N00259Apr 8, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER BASIN, PACKAGE 3, BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTEOn-Going₱149.3M
25N00260Apr 8, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER BASIN, PACKAGE 4, PROTECTING BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTEOn-Going₱149.3M
25N00155Mar 28, 2025LAS NIEVES BRIDGE ALONG NRJ AGUSAN-MALAYBALAY ROAD-BRGY. AMBACON-BRGY. MALICATO-NRJ DAANG MAHARLIKA, PHASE 8, AGUSAN DEL NORTEOn-Going₱93.6M
25N00220Mar 28, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER (AMBACON-PINANA-AN SECTION) DOWNSTREAM, PHASE 3, LAS NIEVES, AGUSAN DEL NORTEOn-Going₱95.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.