Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21OB0069

DPWH infrastructure contract
Contract ID:
21OB0069
Fingerprint:
9269ff9afef8bc…a520f350ae Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 11, 2021 (5 yrs 9 mo ago) · Target/actual end Apr 17, 2022
Description:
CONSTRUCTION OF FOUR (4) STOREY MULTI-PURPOSE BUILDING AT PASIG ELEMENTARY SCHOOL, BARANGAY SAN NICOLAS, PASIG CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
ZYRE TRADING AND CONSTRUCTION · DPWH contractor code 42364
Contract amount:
₱23,752,988.58 (₱23.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d8a193629c5c…Jan 28, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E₱23,752,988.58

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0363Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PATEROS TECHNOLOGICAL COLLEGE, P. HERRERA ST. BRGY. SAN PEDRO, PATEROS (PHASE 1)On-Going₱58.2M
25OB0256Mar 20, 2025CONSTRUCTION OF RETAINING WALL AND REHABILITATION OF STA. ANA RIVER, PATEROS, METRO MANILA (PACKAGE VIII)On-Going₱48.2M
25OB0117Mar 19, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - STO. ROSARIO BR. (B01879LZ) ALONG PPTA RDOn-Going₱9.4M
25OB0272Mar 19, 2025BANK IMPROVEMENT OF SLOPE PROTECTION ALONG MARIKINA RIVER (PACKAGE 21), PASIG CITYOn-Going₱70.2M
25OB0336Mar 19, 2025REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SUMILANG, PASIG CITYCompleted₱14.5M
25OB0337Mar 19, 2025CONSTRUCTION OF BARANGAY TABACALERA BARANGAY HALL, PATEROS, METRO MANILACompleted₱6.8M
25OB0338Mar 19, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, ALVIAR COMPOUND, STA. ANA, PATEROS, METRO MANILATerminated₱0
25OB0339Mar 19, 2025REHABILITATION OF PATEROS ELEMENTARY SCHOOL GYMNASIUM, BARANGAY SAN PEDRO, PATEROS, METRO MANILACompleted₱17.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.