Project 21OB0210
DPWH infrastructure contract
Contract ID:
21OB0210
Fingerprint:
19ed2a55fe7e45…d9232f848c Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start Feb 24, 2022 (4 yrs 8 mo ago) · Target/actual end Oct 28, 2022
Description:
CONSTRUCTION OF PUMPHOUSE INCLUDING PUMPS AT VICTORINO STREET GOING TO MARIKINA RIVER, SANTOLAN, PASIG CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
DAHL CONSTRUCTION CORP. · DPWH contractor code 8931
As listed: DAHL CONSTRUCTION CORP. (FORMERLY: DAHL CONSTRUCTION)
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7de55d6f20b4… | Feb 16, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱13,961,069.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26OB0090 | Jun 22, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - PASIG BLVD C5 FLYOVER (B01876LZ) ALONG C-5 ROAD | On-Going | ₱74.3M |
| 26OB0088 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03319LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱97.8M |
| 26OB0089 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - ORTIGAS BR. (B01868LZ) ALONG MANILA EAST RD (ROSARIO-CAINTA RD) | On-Going | ₱89.9M |
| 26OB0091 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱25.4M |
| 26OB0092 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - DAAN PASIG BR. (B01874LZ) ALONG AMANG RODRIGUEZ RD | On-Going | ₱23.8M |
| 25OB0461 | Jun 20, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM IN PUBLIC FACILITIES IN METRO MANILA 1ST DISTRICT ENGINEERING OFFICE | Completed | ₱2.6M |
| 25OG0038 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
| 25OG0039 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.