Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21OD0196

DPWH infrastructure contract
Contract ID:
21OD0196
Fingerprint:
479780638ff378…213b8eabcd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 27, 2021 (5 yrs 1 mo ago) · Target/actual end Dec 6, 2021
Description:
CONSTRUCTION/ COMPLETION (2- 4STY 8CL) CAMARIN HS, CALOOCAN CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
AYLAN CONSTRUCTION AND TRADING · DPWH contractor code 11884
As listed: AYLAN CONSTRUCTION & TRADING
Contract amount:
₱1,964,980.69 (₱2.0M)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3b19eeee4ec0…Sep 23, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED₱1,964,980.69

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.