Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21OG0111

DPWH infrastructure contract
Contract ID:
21OG0111
Fingerprint:
34a7e686e1d659…9213241461 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 8, 2021 (4 yrs 11 mo ago) · Target/actual end Mar 6, 2023
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH SITE DEVELOPMENT, CAMP AGUINALDO, QUEZON CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Quezon City 2nd DEO · National Capital Region
Contractor:
STEELMAN BUILDERS CORPORATION · DPWH contractor code 32768
Contract amount:
₱24,006,903.23 (₱24.0M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9f2b5a40ef51…Nov 25, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON CITY 2ND ED₱24,006,903.23

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OB0090Jun 22, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - PASIG BLVD C5 FLYOVER (B01876LZ) ALONG C-5 ROADOn-Going₱74.3M
26OB0088May 21, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03319LZ) ALONG C5- ORTIGAS FLYOVER, PHASE IIOn-Going₱97.8M
26OB0089May 21, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - ORTIGAS BR. (B01868LZ) ALONG MANILA EAST RD (ROSARIO-CAINTA RD)On-Going₱89.9M
26OB0091May 12, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5- ORTIGAS FLYOVER, PHASE IIOn-Going₱25.4M
26OB0092May 12, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - DAAN PASIG BR. (B01874LZ) ALONG AMANG RODRIGUEZ RDOn-Going₱23.8M
25OB0461Jun 20, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM IN PUBLIC FACILITIES IN METRO MANILA 1ST DISTRICT ENGINEERING OFFICECompleted₱2.6M
25OG0038May 23, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITYOn-Going₱48.0M
25OG0039May 23, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITYOn-Going₱48.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.