Project 21PE0049
DPWH infrastructure contract
Contract ID:
21PE0049
Fingerprint:
a6889f212c2c35…35fd457b27 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 21, 2021 (5 yrs 3 mo ago) · Target/actual end Apr 12, 2022
Description:
CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - CONG. ANDRES ACOP COSALAN RD. - K0318+428 - K0318+463, K0318+930 - K0318+948, K0323+112 - K0323+134, K0323+840 - K0323+866, K0331+1260 - K0331+1292, K0331+1381 - K0331+1398, K0331+1617 - K0331+1668, K0333+
Category:
Roads
Implementing office:
DPWH Benguet 1st DEO · Cordillera Administrative Region
Contractor:
M.P. TABERAO CONSTRUCTION SERVICES AND SUPPLIES (46017) / R.S. SEPIAN CONSTRUCTION & TRUCKING · DPWH contractor code 20519
Contract amount:
₱68,195,606.18 (₱68.2M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26PE0016 | Jul 30, 2026 | CONSTRUCTION OF CONCRETE ROAD - POBLACION-KARAO-EKIP ACCESS ROAD LEADING TO MOUNT PURGATORY - 0+822 - 0+942, BOKOD, BENGUET | On-Going | ₱4.3M |
| 26PE0014 | Jul 7, 2026 | CONSTRUCTION OF CONCRETE ROAD ALONG KAWAL TO BISAL - 2+442 - 4+137, BOKOD, BENGUET | On-Going | ₱28.8M |
| 26PE0022 | Jul 7, 2026 | CONSTRUCTION OF 3STY-12CL MULTI-PURPOSE BUILDING AT AMBUKLAO NATIONAL HIGH SCHOOL (SCHOOL ID: 305163), BRGY. AMBUKLAO, BOKOD, BENGUET | On-Going | ₱36.6M |
| 25P00006 | Dec 16, 2025 | IMPROVEMENT OF ROAD, KAWAL TO BISAL, PHASE I, BARANGAY BOBOK - BISAL, BOKOD, BENGUET | On-Going | ₱48.1M |
| 25PE0034 | Mar 31, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - BENGUET - NUEVA VIZCAYA RD (S00382LZ) - K0305+243 - K0305+260, BOKOD, BENGUET | Completed | ₱5.6M |
| 25PE0013 | Mar 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - BILA ACCESS ROAD LEADING TO ABIANG HOT SPRING, BOKOD, BENGUET | Completed | ₱12.8M |
| 25PE0008 | Feb 17, 2025 | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - BENGUET-NUEVA VIZCAYA RD (S00382LZ) - K0276 + 145 - K0280 + 710, K0280 + 741 - K0281 + 500, BOKOD, BENGUET | Completed | ₱23.5M |
| 25PE0010 | Feb 17, 2025 | RETROFITTING/STRENGTHENING OF BRIDGE - TAAL BR. (B00907LZ) ALONG BENGUET-NUEVA VIZCAYA RD., BOKOD, BENGUET | Completed | ₱7.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.