FY2026 GAA: ₱6.79T
PisoScan

Project 22AD0062

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","22AD0062","CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF SAN ANTONIO RIVER CONTROL STRUCTURE, BARANGAY SAN ANTONIO, NARVACAN, ILOCOS SUR","Flood Control and Drainage","Completed",86849854.45,0,100,"Ilocos Sur 2nd DEO","Region I","739 BUILDERS (31174)","2022-02-24","2023-04-17",2022,"Regular Infra - GAA 2022 OO-2",17.40863,120.48736,"102914000","102900000"]
SHA-256
14c4119ad7bf091a9617215c85835748cf798f5695b97478594a6cbba991f84c

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.