Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22AH0061

DPWH infrastructure contract
Contract ID:
22AH0061
Fingerprint:
040ebd595d8bb6…e568996e70 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2022 (4 yrs 9 mo ago) · Target/actual end Sep 19, 2022
Description:
CONST'N.OF RD.INCL.DRAINAGE SYSTEM IN BRGYS.BARI TO MALABAGO ALONG MANGALDAN SLAUGHTERHOUSE & LIVEST
Category:
Roads
Implementing office:
Contract amount:
₱48,996,828.09 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0126Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. BUENLAG,MANGALDAN,PANGASINANOn-Going₱2.9M
25AH0130Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. GUESANG,MANGALDAN,PANGASINANOn-Going₱1.9M
25AH0131Jun 11, 2025REHABILITATION OF ROAD, BARANGAY AMANSABINA,MANGALDAN, PANGASINANCompleted₱4.8M
25AH0173Mar 21, 2025CONCRETING OF BRGY. MALABAGO-BRGY.ALITAYA SERVICE ROAD FMR,BRGY. MALABAGO,MANGALDAN,PANGASINANCompleted₱14.4M
25AH0174Mar 21, 2025CONCRETING OF BRGY. SALAAN FMR,BRGY. SALAAN,MANGALDAN,PANGASINANCompleted₱14.5M
25AH0127Mar 20, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. POBLACION,MANGALDAN,PANGASINANCompleted₱1.9M
25A00286Feb 25, 2025WIDENING OF PERMANENT BRIDGES - EMBARCADERO BR. (B01329LZ) ALONG MANGALDAN-MANAOAG-BINALONAN RD (PHASE II)On-Going₱93.6M
25AH0077Feb 25, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MANGALDAN, PANGASINANOn-Going₱3.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.