Project 22BA0043

DPWH infrastructure contract
Contract ID:
22BA0043
Fingerprint:
d17de2e73d83a6…9bdc690bb0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2022 (4 yrs 7 mo ago) · Target/actual end Dec 31, 2022
Description:
CONSTRUCTION OF FLOOD CONTROL SAVANG-AKSUNG, BRGY. NAKANMUAN, SABTANG, BATANES
Category:
Flood Control and Drainage
Implementing office:
DPWH Batanes DEO · Region II
Contractor:
CVAP CONSTRUCTION · DPWH contractor code 20410
Contract amount:
₱8,338,455.58 (₱8.3M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fd1671ff432c…Mar 14, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANES DEO₱8,338,455.58

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BA0065Aug 27, 2025CONSTRUCTION OF EVACUATION CENTER, SABTANG, BATANESOn-Going₱51.5M
25BA0039Jun 18, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS: SAN VICENTE- SAVIDUG- CHAVAYAN- SUMNANGA- NAKANMUAN ROAD, CHAVAYAN, PACKAGE 1, BATANESOn-Going₱49.9M
25BA0073Jun 18, 2025BIP- MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (SABTANG MUNICIPAL BUILDING), PHASE II, BARANGAY SINAKAN, SABTANG, BATANESOn-Going₱28.9M
25BA0003Mar 31, 2025ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- TERTIARY ROADS:SAN VICENTE-SAVIDUG-CHAVAYAN-SUMNANGA- NAKANMUAN ROAD -K0005+871.20-K0006+022.00Completed₱7.4M
25BA0008Mar 27, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGE: SAVIDUG BRIDGE (B00003ST) ALONG SAN VICENTE - SAVIDUG - CHAVAYAN- SUMNANGA - NAKANMUAN ROADCompleted₱9.5M
25BA0001Mar 26, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- TERTIARY ROADS: SAN VICENTE- SAVIDUG- CHAVAYAN- SUMNANGA- NAKANMUAN ROAD - K0022+424-K0022+542Completed₱4.2M
25BA0002Mar 25, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- TERTIARY ROADS:SAN VICENTE-SAVIDUG-CHAVAYAN- SUMNANGA-NAKANMUAN ROAD - K0024+605-K0024+646Completed₱1.4M
25BA0009Mar 20, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: CONSTRUCTION OF NEW BRIDGES: VUYUAN BRIDGE ALONG SAN VICENTE- SAVIDUG- CHAVAYAN- SUMNANGA- NAKANMUAN ROADCompleted₱10.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.