Project 22BE0108
DPWH infrastructure contract
Contract ID:
22BE0108
Fingerprint:
0f67455ad04ee1…e16097e285 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 25, 2022 (4 yrs 2 mo ago) · Target/actual end Nov 15, 2022
Description:
CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), CITY OF ILAGAN, TUMAUINI, CABAGAN, DELFIN ALBANO, STO. TOMAS, SAN PABLO, & STA. MARIA, ISABELA
Category:
Water Provision and Storage
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
SMT CONSTRUCTION · DPWH contractor code 36331
Contract amount:
₱2,867,301.87 (₱2.9M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a97f13f0199a… | Aug 10, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO | ₱2,867,301.87 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0168 | Jun 17, 2026 | CONSTRUCTION OF CLASSROOMS, CANDANUM INTEGRATED SCHOOL, CABAGAN, ISABELA | On-Going | ₱28.5M |
| 25BE0143 | Jan 22, 2026 | CONCRETING OF SITIO PELO, BRGY. CANSAN FMR, BRGY. CANSAN, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0131 | Sep 16, 2025 | CONSTRUCTION OF SCHOOL BUILDING, CUBAG INTEGRATED SCHOOL, BARANGAY CUBAG, CABAGAN, ISABELA | Completed | ₱19.3M |
| 24BE0183 | Aug 20, 2025 | CONSTRUCTION OF SEWAGE TREATMENT PLANT, MILAGROS ALBANO DISTRICT HOSPITAL, CABAGAN, ISABELA BARANGAY NGARAG, CABAGAN, ISABELA | On-Going | ₱28.1M |
| 25BE0078 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY AGGUB, CABAGAN, ISABELA | On-Going | ₱9.6M |
| 25BE0082 | Jul 14, 2025 | CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0089 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CAGAYAN | On-Going | ₱140.3M |
| 25BE0090 | Jul 14, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUR | On-Going | ₱93.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.