Project 22CC0038
DPWH infrastructure contract
Contract ID:
22CC0038
Fingerprint:
01d05c4672e194…1d30356927 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 4, 2022 (4 yrs 9 mo ago) · Target/actual end Nov 21, 2022
Description:
REHABILITATION OF RIVER CONTROL STRUCTURES ALONG BOCAUE RIVER, SULUCAN, BOCAUE, BULACAN
Category:
GAA 2022 CSSP
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
BLACK HARDHAT INC. (FORMERLY: JCHARDHAT INC.) (49520) / TOPNOTCH CATALYST BUILDERS INC. · DPWH contractor code 34061
Contract amount:
₱45,079,631.44 (₱45.1M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0469 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY MALAWAK, BUSTOS, BULACAN | On-Going | ₱18.3M |
| 25CC0470 | May 23, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (SPORTS COMPLEX), POBLACION, BUSTOS, BULACAN | On-Going | ₱29.0M |
| 25CC0492 | May 23, 2025 | CONSTRUCTION OF ROAD AT BARANGAY TALAMPAS , BUSTOS, BULACAN | On-Going | ₱47.6M |
| 25CC0534 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TANAWAN, BUSTOS, BULACAN | On-Going | ₱19.3M |
| 25CD0219 | Apr 15, 2025 | IMPROVEMENT OF NORZAGARAY-ANGAT-BUSTOS DIVERSION ROAD IN NORZAGARAY AND ANGAT, BULACAN | On-Going | ₱4.8M |
| 25CC0210 | Apr 8, 2025 | CONSTRUCTION OF ROAD AT BARANGAY LICIADA, BUSTOS, BULACAN | On-Going | ₱9.4M |
| 25CC0393 | Apr 8, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUSTOS, BULACAN | On-Going | ₱14.5M |
| 25CC0504 | Apr 4, 2025 | REHABILITATION OF BRIDGE, PUROK 7, BARANGAY BONGA MAYOR, BUSTOS, BULACAN | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.