Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22CE0098

DPWH infrastructure contract
Contract ID:
22CE0098
Fingerprint:
31391a8994ff92…1549af4c9b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2022 (4 yrs 8 mo ago) · Target/actual end Aug 22, 2022
Description:
NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - MUÑOZ - LUPAO RD K0148+300 - K0149+000, K0152+371 - K0153+000, K0155+515 - K0156+000, K0163+000 - K0164+000
Category:
Roads
Implementing office:
Contractor:
Contract amount:
₱25,151,153.94 (₱25.2M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0355Dec 3, 2025CONSTRUCTION OF SCHOOL HEALTH FACILITIES, MUNOZ CS, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱4.9M
25CE0302Jul 30, 2025CONSTRUCTION OF CLASSROOM BUILDING AT CENTRAL LUZON STATE UNIVERSITY, MUNOZ, NUEVA ECIJACompleted₱19.7M
25CE0203Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LICAONG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱5.9M
25CE0204Jul 1, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALIGAYA ES, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱3.0M
25CE0206Jul 1, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN FELIPE, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱4.9M
25CE0213Jul 1, 2025REPLACEMENT OF BOX CULVERT ALONG MUNOZ-TALUGTUG ROAD, BARANGAY CALISITAN, MUÑOZ, NUEVA ECIJACompleted₱11.6M
25CE0205Jun 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJACompleted₱5.9M
25CE0218Jun 30, 2025CONSTRUCTION OF WATER SYSTEM, BARANGAY VILLA ISLA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJAOn-Going₱4.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.